A Joint Infrastructure-delivery Project

June 25, 2021

City & Metro District Launch Joint $3.6 Million Infrastructure-Delivery Project

“We approached the City last year with the idea of delivering both infrastructure projects, simultaneously, and thereby leveraging, saving, and stretching taxpayer dollars. Our collaborative, multi-jurisdictional approach to replacing essential infrastructure is efficient, fiscally responsible, and will benefit every resident, business owner, worker, and commuter in our community,” said CPNMD President David McEntire.

Media Release: Metro District & City Launch Joint $3.6 Million Infrastructure-Delivery Project

JULY ALERT!

  • Crews are currently out excavating, laying pipe, removing inlets, and pouring concrete for inlets for the remainder of the week. Next up will be grading and putting in base course to start asphalt.

  • Eastbound lane closures on Castle Pines Parkway continue. (See map below.)

  • Demolition of the southern-most lane of Castle Pines Parkway continues.

  • Please avoid Castle Pines Parkway between Monarch on the west and Yorkshire Drive on the east. Alternate routes advised. (See map below.)

  • Temporary access closure between Shoreham Drive and Castle Pines Parkway continues. Use Monarch Boulevard as an alternate route. (See map below.)

QUESTIONS?

  • Please contact us with questions via our web-based form here or call (303) 688-8550. In case of an emergency, please update your contact info with us here. Remind your family and neighbors to do the same.

JULY SCHEDULE

  • Crews are currently out excavating, laying pipe, removing inlets, and pouring concrete for inlets for the remainder of the week. Next up will be grading and putting in base course to start asphalt.
  • Full eastbound lane closure begins June 21, 2021
  • Construction begins: June 21, 2021 – alternate routes are advised
  • Anticipated completion: December 2021

JULY TRAVEL IMPACTS

Anyone traveling this corridor can expect throughout the project:

  • Construction work Monday through Friday, during the hours of 7:00 a.m. to 5:30 p.m.
  • Though alternate routes are advised due to likely delays, Castle Pines Parkway will remain open to single-lane traffic in both directions.
  • Sidewalk closures on the north side of Castle Pines Parkway for pedestrians.
  • Bicycle lane closures.
  • There will be various neighborhood entry closures at different times during the project. We will suggest alternate routes as necessary.