A Joint Infrastructure-delivery Project

June 25, 2021

City & Metro District Launch Joint $3.6 Million Infrastructure-Delivery Project

“We approached the City last year with the idea of delivering both infrastructure projects, simultaneously, and thereby leveraging, saving, and stretching taxpayer dollars. Our collaborative, multi-jurisdictional approach to replacing essential infrastructure is efficient, fiscally responsible, and will benefit every resident, business owner, worker, and commuter in our community,” said CPNMD President David McEntire.

Media Release: Metro District & City Launch Joint $3.6 Million Infrastructure-Delivery Project

SEPTEMBER 2021 ALERT!

  • This week crews are installing the rest of the storm piping and edge drain as well as pouring concrete manholes. Additionally, they are removing and reinstalling the southeast curb and gutter at Monarch and a few concrete panels in the road (all in the construction zone). These activities will head into next week as well. The end of next week will include grading and laying the base course.

  • Temporary access closure to Shoreham Dr. from Castle Pines Parkway began 6/21. Use Monarch Blvd. as alternate route. (See map below.)

  • Demolition of the southern-most lane of Castle Pines Parkway continues.

  • Left turns from Castle Pines Parkway onto Yorkshire Dr. are currently not permitted when traveling westbound. (See map below.)

  • Temporary access closure between Shoreham Drive and Castle Pines Parkway continues. Use Monarch Boulevard as an alternate route. (See map below.)
  • Until further notice, the contractor will also be working Saturdays 8:00 a.m. to 4:00 p.m.

QUESTIONS?

  • Please contact us with questions via our web-based form here or call (303) 688-8550. In case of an emergency, please update your contact info with us here. Remind your family and neighbors to do the same.

SEPTEMBER 2021 SCHEDULE

  • Crews are currently out excavating, laying pipe, removing inlets, and pouring concrete for inlets for the remainder of the week. Next up will be grading and putting in base course to start asphalt.
  • Full eastbound lane closure begins June 21, 2021
  • Construction begins: June 21, 2021 – alternate routes are advised
  • Anticipated completion: December 2021

SEPTEMBER 2021 TRAVEL IMPACTS

Anyone traveling this corridor can expect throughout the project:

  • Construction work Monday through Friday, during the hours of 7 a.m. to 5:30 p.m. and until further notice contractor will be working Saturdays 8:00 a.m. to 4:00 p.m.
  • Full eastbound lane closures followed by full westbound lane closures after work on the eastbound side has been completed.
  • Castle Pines Parkway to remain open to single-lane traffic in both directions, though alternate routes are advised due to likely delays.
  • Potential sidewalk closures on the north side of Castle Pines Parkway for pedestrians.
  • Bicycle lane closures.
  • Various neighborhood entry closures at different times during the project. Suggested alternate routes will be provided as necessary.